Glenclair Environmental Plantings
Reforest 1,334 hectares of Northern Tablelands country with native species to generate ACCUs and restore biodiversity corridors.
About This Project
A large-scale Environmental Plantings project across 1,334 hectares of the Glenclair Aggregation. Modelled via FullCAM under the Reforestation by Environmental or Mallee Plantings 2024 method. The project is designed to generate approximately 954,040 ACCUs over 25 years — the highest total ACCU yield in the Fresh Earth portfolio. Planting operations share infrastructure and staff with the neighbouring Talbingo property.
Project Economics
Modelled projections based on FullCAM/PLANR methodology and CER floor pricing. Values are estimates — not guaranteed outcomes. Net flows to Earth Treasury after design, supply and operation costs are accounted for.
After design, supply and operation costs — transparent project expenses verified at each stage — the net value from Glenclair Environmental Plantings flows to the Earth Treasury. CSF equity backs the platform company that makes this measurement and verification possible.
Project Timeline
Confirmed milestones are solid. Estimated future milestones are shown dashed — subject to regulatory decisions and operational scheduling.
- Tucker Environmental assessmentJun 2025
- CER registeredJul 2025
- Planting operations begin~Autumn 2026estimated
- Establishment verified~Q1 2027estimated
- First ACCUs issued~2028estimated
Project Partners
Impact Progress
Native trees and shrubs planted on land that was previously cleared. Carbon stored in the growing vegetation is measured using the FullCAM model. Planting must survive establishment; ACCUs are issued only after independent audit confirms sequestration.
Back the platform that verifies Glenclair Environmental Plantings and every project like it.
The CSF raise funds Fresh Earth Universe Pty Ltd — the company building the operating system, legal infrastructure, and verification platform. Farm projects are funded through Earth Currency (FELT), issued after the platform is built.